WP01 - Project Management

Lead contractor:
UNIPD - Università degli Studi di Padova
Involved participants:
BAM, BOZZA, CDCU, ENA, GUNI, IAA, IPM, ITAM, CINTEC, MONU, UNIPD, NTUA, POLIMI, S&B, UBATH, UMINHO, UPC, ZRS
ActivityType: MGT Start month: 1 End month: 36 Persons month: 33

Objectives

  • To perform the global scientific management of the project and co-ordinate single workpackages;
  • To co-ordinate the flow of information among partners and relevant input/output between WPs;
  • To control the time schedule, manage costs, effort and modifications, communicate with the EC;
  • To create a dedicated website with public and private access for communication and exchange of information among partners. 

Subtasks

  • WP1.1: Overall management of the project;
  • WP1.2: Internal coordination of WPs.

Deliverables

  • Project Website (D1.1), delivered at PM3 and regularly updated;
  • First progress report (D1.2), delivered at PM9;
  • Mid-term report, including management and financial reports (D1.3), delivered at PM18;
  • Third progress report (D1.4), delivered at PM27;
  • Final report, including management and financial reports; ‘Final plan for the use and dissemination of foreground’, and ‘Report on the awareness and wider societal implications’ (D1.5), after PM36.
assets/Images/Extra/_resampled/SetWidth48-gear.png

Project Management, lasting for the whole duration of the project and aimed at coordinating and monitoring all the activities, verifying the successful achievement of the expected milestones. It will be assessed through the public access to the project website and data base (M1 at PM3) and by the regular six-monthly meetings and reports (M2, during the project).